Case Analysis · Argentina · Copper · Power Infrastructure · Updated August 2026

Josemaría Power Corridor
Who Controls Argentina’s Copper Grid?

Resolution 330/2026 has approved Josemaría’s 260 MW grid access and the associated 500 kV expansion. The commercial question now shifts from regulatory approval to execution, procurement and the capacity available for the next mining projects.

Marcus A. Volz San Juan · Electricity · Mining Infrastructure Econosur · Published 16 July 2026 · Updated 18 August 2026
Josemaría power corridor and 500 kV mining electricity infrastructure in San Juan, Argentina
The approved federal expansion links Josemaría to the Argentine grid through Nueva San Juan, Rodeo and a new high-altitude node at Chaparro.
25 years Priority period established under Resolution 79/2026 and ratified by Resolution 330/2026.
260 MW Initial electricity demand requested for Josemaría Phase 1
167 km Authorized new 500 kV line between Rodeo and Chaparro
545.7 MVA Derived priority on Nueva San Juan–Rodeo, ratified by Resolution 330
90% Maximum priority granted over specified remaining or newly created capacity
Research Case Framework

From regulatory evidence to commercial implications

Business Question

Who controls the infrastructure and procurement decisions behind Josemaría’s grid connection — and what does this mean for suppliers and later mining projects?

Evidence Examined

Resolutions 79/2026, 219/2026 and 330/2026, the official public-hearing transcript, regulator documentation, company information and related infrastructure evidence.

Finding

Federal approval and Vicuña’s priority are established. The main unresolved commercial issues are package ownership, tender timing, contractor structure and practical capacity for later users.

Commercial Implication

The opportunity is shifting from regulatory approval toward engineering, procurement, contractor selection, supplier qualification and the next phase of grid expansion.

Quick answer

The Josemaría power corridor has moved from regulatory dispute to approved infrastructure.

Resolution 330/2026 authorized 260 MW of grid access for Josemaría Phase 1 and issued the Certificate of Public Convenience and Necessity for the 500 kV expansion requested by Transener on behalf of Vicuña Argentina.

The resolution rejected the objections filed in the proceeding and ratified Vicuña’s priority rights on the incremental capacity identified on Nueva San Juan–Rodeo, the new 167 km Rodeo–Chaparro line and the new Chaparro substation. The next commercial questions concern execution: package design, procurement timing, contractor selection, technical compliance and the additional capacity that later mining projects may require.

Status after Resolution 330/2026: the federal regulatory decision was issued on 28 July 2026 and published on 29 July. It authorizes the 260 MW access request, approves the main transmission expansion, rejects the filed objections and ratifies the priority structure established in Resolution 79. Approval does not mean the infrastructure has been built or that contracts have been awarded. Vicuña must still meet technical, easement and execution requirements, while project sanction and procurement remain separate commercial milestones.

The case sits at the centre of Argentina’s emerging copper economy. The country’s advanced projects are not simply waiting for financing and permits. They are competing for roads, water, grid nodes, transformer capacity and rights over infrastructure built in earlier development cycles.

That changes the commercial question. Josemaría does not merely require electricity. It requires a regulatory structure capable of converting a private mining demand into permanent regional infrastructure without making the same infrastructure inaccessible to the next project.

The conflict begins where privately financed expansion meets a corridor that already has a public and multiuser history.

Why Josemaría needs a new power corridor

Vicuña Corp. presented an initial demand of approximately 260 MW for Josemaría Phase 1. At the June hearing, the company said demand could later increase to around 400 MW and approximately 700 MW through successive stages of the district plan.

The initial load is already industrially significant. Vicuña described the project as electricity-intensive because crushing, grinding and mineral processing require a robust connection point, stable voltage and sufficient short-circuit strength. The current regional system cannot simply absorb a load of this scale without major transport works.

The corridor is therefore not an optional improvement. Vicuña described the federal access and expansion approval as a critical condition for converting project preparation into executable infrastructure contracts, construction schedules and eventual operations.

Project boundary: the federal proceeding concerns 260 MW for Josemaría Phase 1. The later 400 MW and approximately 700 MW figures are Vicuña’s stated development trajectory, not the demand formally approved in the current access case.

The infrastructure package has five layers

The connection architecture extends from the mine to the national interconnected grid. It combines project-owned facilities, authorized federal transmission assets and an upgrade of an existing line.

Josemaría connection architecture
ET Josemaría Project-side substation forming part of Vicuña’s internal facilities.
Josemaría–Chaparro Approximately 93 km of double-circuit 220 kV line connecting the mine to the new federal node.
ET Chaparro New 500/220 kV GIS substation at roughly 3,000 metres, with a 450 MVA transformer and two 220 kV exits to Josemaría.
Rodeo–Chaparro New single-circuit 500 kV line of approximately 167 km across terrain reaching about 3,500 metres.
ET Rodeo New 500 kV yard, 600 MVA 500/132/33 kV transformation and connection to the existing regional system.
Nueva San Juan–Rodeo Existing line currently operated at 132 kV, to be disconnected from the 132 kV yards and energized through new 500 kV fields.

Once enabled, the federal 500 kV works would enter the SADI and be operated and maintained by Transener. Vicuña promotes and finances the expansion; it does not become the transmission operator.

The design also creates optionality beyond the mine. Chaparro includes space for future transformation and possible interconnections toward La Rioja Sur and Catamarca. Rodeo provides room for further expansion, while the new system could support future mining demand and renewable generation in northern San Juan.

Resolution 330 confirmed the priority structure established in Resolution 79

Resolution 79/2026 established three priority layers for Vicuña. After the June public hearing and the objections summarized in this analysis, Resolution 330/2026 ratified those priorities rather than narrowing them.

90% of 71%
Priority on the capacity CAMMESA classified as remaining on Nueva San Juan–Rodeo after energization at 500 kV
Up to 90%
Priority on the new 167 km Rodeo–Chaparro 500 kV line
Up to 90%
Priority on the new Chaparro 500/220 kV, 450 MVA substation

CAMMESA’s calculation treated 71 per cent of an assumed 854 MVA total corridor capacity as remaining. Ninety per cent of that remainder produces approximately 545.7 MVA. Resolution 330 explicitly ratified this priority on Nueva San Juan–Rodeo and the priorities on the new Rodeo–Chaparro line and Chaparro substation.

The regulator also maintained the distinction around Rodeo’s new 600 MVA transformer. The earlier decision had not granted Vicuña equivalent priority over that transformer because its loading was not considered to depend appreciably on Vicuña’s demand. Resolution 330 left that structure intact.

MW and MVA are not interchangeable. Josemaría’s 260 MW demand is real power; the 545.7 MVA priority is apparent-power capacity. The figures should not be compared as if they were the same unit. The objections focused on whether the reserved capacity was proportionate to the project’s verified demand and the works it finances. Resolution 330 rejected those objections and ratified the priority framework.

The case contains two legally different infrastructures

The strongest objection separates the corridor into a pre-existing section and a new section.

Rodeo–Chaparro is a new line. It does not yet exist, and Vicuña proposes to finance its 167 kilometres of 500 kV infrastructure together with the new Chaparro node. A priority right can therefore be defended as an incentive for creating capacity that would otherwise not be built.

Nueva San Juan–Rodeo already exists. The physical line was built through a mixture of federal and provincial funds, electricity-user contributions and earlier mining payments. Vicuña’s project would change the terminal configuration and energize the link at 500 kV, but it would not create the entire corridor from nothing.

This distinction is the core of the case. A single regulatory priority was applied across infrastructure with different financing histories and different relationships to Vicuña’s demand.

A private investor can create new capacity without having created the entire corridor on which that capacity depends.

Vicuña’s argument: priority makes private infrastructure bankable

Vicuña’s position is that a mine cannot finance and schedule a multibillion-dollar development around uncertain electricity access. The company therefore needs secured availability compatible with the life of the project and the successive stages of its demand.

At the hearing, Vicuña argued that Resolution 79 did not give it control over San Juan’s electricity system and did not abolish open access. It described the priority as applying to incremental capacity generated by specific works that it promotes and finances. Other users could still request further expansions.

This is the investment-incentive case. Without a protected right to use the capacity it pays to create, a private developer could face a free-rider problem: it finances the infrastructure, while later users consume the capacity without sharing the original risk or cost.

The Instituto Argentino de la Energía General Mosconi supported this underlying logic at the hearing. Its contribution was not a blanket endorsement of every priority term, but a warning that immediate unrestricted access can destroy the incentive for private transmission investment.

San Juan’s position: the new demand must internalize system costs

EPRE San Juan supports mining development but conditioned its opposition on a system-mitigation agreement.

The provincial regulator argued that Vicuña’s load and the voltage conversion would change regional power flows, increase pressure on transformation infrastructure and potentially advance other network investments. Those effects should not be transferred to households, commerce or unrelated industries through tariffs or deteriorating service quality.

EPRE also argued that today’s corridor resulted from long-term planning and mixed financing. At the hearing it stated that earlier mining companies had contributed a total of US$133.8 million to provincial public funds used to expand and consolidate the network. That number is EPRE’s stated historical accounting position, not an independent valuation performed by Econosur.

The requested solution was not simply rejection. EPRE sought:

  • a formal mitigation agreement between Vicuña and San Juan;
  • internalization of system costs caused by the new mining demand;
  • protection of service reliability for existing users;
  • recognition of earlier financing rights; and
  • availability of capacity beyond Vicuña’s actual requirements for other projects.

Los Azules challenges the model behind the capacity

Andes Corporación Minera, the Argentine project company for Los Azules, did not reject the principle of priority on newly financed capacity. It challenged the technical base and the extension of that priority onto the existing trunk corridor.

The first objection concerns the 854 MVA capacity assumption. According to Resolution 219 and the hearing transcript, Andes argued that the number was not a measurement under current operating conditions. It came from a model that treated Nueva San Juan as an “infinite power bus” — a strong-node assumption that CAMMESA itself described as not matching the system’s current condition and as dependent on future generation, synchronous compensation or other works outside Vicuña’s package.

The second objection is multiuser planning. A study commissioned by Andes modelled simultaneous 2030 demand from:

260 MW
Vicuña / Josemaría in the objector’s 2030 scenario
140 MW
Los Azules in the objector’s commissioned model
300 MW
El Pachón in the same multiuser scenario

Andes stated that its study produced a corridor capacity between 645 and 745 MVA rather than 854 MVA. Under those assumptions, the 545.7 MVA priority would absorb between 73.2 and 84.6 per cent of the modelled real corridor capacity, leaving 99 to 199 MVA for other users.

Evidence boundary: the 645–745 MVA range, the 2030 multiuser scenario and the resulting percentages are findings of a study commissioned by Andes Corporación Minera and summarized in Resolution 219. They are not a final capacity determination by CAMMESA or the regulator.

Andes therefore requested a narrower priority, periodic review, release of unused capacity, separate treatment of the existing Nueva San Juan–Rodeo section and the new Rodeo–Chaparro section, and an integrated regional study that includes other mining demand.

Earlier mines claim that financing created rights

The corridor was not financed through one clean public-private transaction. Several earlier projects claim rights based on agreements, provincial legislation and direct contributions.

Historical capacity claims presented at the hearing
Barrick / Minera Andina del Sol Stated that the companies contributed US$55 million to Nueva San Juan–Rodeo and had an expectation of access up to 250 MW under provincial agreements and legislation.
Gualcamayo Minas Argentinas sought recognition of a claimed 30 MW position linked to earlier agreements and infrastructure participation.
Casposo Claimed protection for up to 20 MW and argued that financial rights of earlier initiators should be addressed before allocating new priority.
Hualilán Raised future connection requirements and argued that the corridor must preserve access for an approved project already advancing in San Juan.

These claims are not equivalent to a final federal capacity award. They demonstrate that the corridor already carries a contractual and political history that cannot be reduced to a simple calculation of unused megavolt-amperes.

La Rioja wants a future place in the network

La Rioja’s intervention gives the case an interprovincial dimension. The province sought recognition of its earlier participation and requested that the Chaparro design preserve the technical possibility of a future 500 kV connection toward La Rioja Sur.

Its position was that a final approval should not close regional expansion options or leave La Rioja to finance all future works created by the new system configuration. Chaparro’s planned space for future links toward La Rioja and Catamarca therefore has regulatory as well as engineering significance.

The power dispute mirrors the separate road conflict around Vicuña. The deposit is located in San Juan, but major infrastructure decisions affect neighbouring provincial systems and create bargaining positions outside the immediate mine site.

The corridor tests Argentina’s new private-infrastructure model

Resolution 330 gives a clear regulatory answer to the immediate dispute: the federal regulator accepted the private-investment logic and ratified Vicuña’s priority rights while maintaining that they apply to incremental capacity rather than ownership or control of the public grid.

That decision does not remove the wider multiuser problem. As Los Azules, El Pachón, Hualilán and other projects advance, the system will still need rules and additional investment that reconcile private financing with open access and future demand.

A workable long-term model therefore still needs at least five elements:

Elements of a bankable multiuser model
Causal priority Priority should correspond to capacity actually created or required by the initiating project.
Unused-capacity release Capacity not used within defined milestones should return to the open-access pool.
Periodic review Demand, project stages and system conditions should be reassessed during a 25-year period.
Cost allocation New users should internalize direct and systemic costs while historical financing rights are identified.
Multiuser planning Los Azules, El Pachón, Hualilán, gold operations, provincial demand and future generation need a common network model.
Expansion pathway Future users need a defined mechanism to finance additional lines, transformation and compensation.

This is why the corridor matters beyond one mine. Resolution 330 is now an observable precedent for how Argentina can authorize privately financed mining infrastructure that becomes part of a wider public system. The next test is whether later projects can connect without recreating the same capacity conflict.

The regulatory file describes a real supplier market

The proceeding is also a procurement map. Transener’s hearing presentation identifies engineering packages that go far beyond a line-construction contract.

Potential equipment and service layers
500 kV and 220 kV GIS Indoor high-altitude switchgear, building systems, installation and commissioning at Chaparro.
Power transformers 600 MVA and 450 MVA banks, reserve phases, transport, erection, testing and maintenance support.
Reactive compensation Bus and line reactors, possible dynamic compensation and voltage-control systems.
Protection and automation Relays, measurements, control, communications, demand-shedding automation and station auxiliary systems.
Transmission structures Cross-rope and self-supporting towers, conductors, OPGW, foundations and high-altitude construction logistics.
Power-quality engineering Load-flow, stability, harmonic, flicker and electromagnetic-transient studies.

The regulatory file describes technical requirements, not awarded contracts. Resolution 330 removes the main federal approval uncertainty for the transmission package, but supplier opportunity still depends on project sanction, detailed engineering, package design, financing and the procurement route selected by Vicuña, Transener and their contractors.

The distinction matters. Regulatory approval reveals a defined infrastructure requirement, but it does not identify the final EPC or EPCM structure, bidder list, qualification route or equipment awards. Those commercial details are not established by the public decision.

What remains open after Resolution 330

Execution and commercial questions
  • When the approved transmission packages will move into detailed procurement and construction.
  • How package ownership will be divided among Vicuña, Transener and future EPC or EPCM contractors.
  • Which suppliers will be prequalified for GIS, transformers, protection, automation, towers, conductors and high-altitude construction.
  • How Vicuña will satisfy the technical requirements imposed by Transener, CAMMESA, Distrocuyo, Naturgy San Juan and ENReGE.
  • How easements, land access and final engineering will affect the construction schedule.
  • How much usable capacity will remain as Los Azules, El Pachón, Hualilán and other regional demand advances.
  • Which additional transmission, compensation or transformation works later users may need to finance.
  • How the timing of the power corridor will align with Vicuña’s project sanction and wider Stage 1 execution schedule.

The regulatory decision therefore closes one question but opens the commercial phase. The corridor is authorized. What public information still does not show is the precise contracting sequence, supplier field, package timing and multiuser capacity picture that will determine who participates in execution and how quickly later projects can connect.

Econosur assessment

Market Reality: Josemaría’s 260 MW demand now has federal authorization for the transmission expansion required to connect it. The regulatory risk has narrowed, while engineering, financing, procurement and construction risk become more important.

Control Question: Resolution 330 accepted the regulator’s view that Vicuña’s priority applies to incremental capacity created by the privately financed expansion, including the 500 kV energization of Nueva San Juan–Rodeo. The practical question now is how that priority interacts with later mining demand.

Commercial Interpretation: the decision shifts attention toward execution. Suppliers, contractors and competing projects need to understand who will buy each package, when procurement starts, which qualification routes apply and what additional grid expansion may be required as San Juan’s copper pipeline advances.

Business questions behind the Josemaría power corridor

1. Which Josemaría power packages are closest to procurement, and who controls each buying decision?

Resolution 330 defines the approved infrastructure with unusual technical clarity: Nueva San Juan and Rodeo upgrades, a 167 km 500 kV line, the new Chaparro GIS substation, large transformer banks, protection and control systems and associated transmission works. That establishes demand, but it does not establish the current commercial sequence.

For suppliers, the missing information is who owns each package, whether procurement will sit with Vicuña, Transener or an EPC or EPCM contractor, which packages are already in prequalification, what bidder lists are being built and when technical requirements become purchase orders. Tender monitoring, contractor mapping and direct supplier checks can turn the approved engineering scope into a usable procurement map.

2. How much usable grid capacity will remain for Los Azules and other San Juan projects after Vicuña’s priority is applied?

Resolution 330 ratifies Vicuña’s priority and accepts the regulator’s argument that the relevant right applies to incremental capacity created by the expansion. The proceeding also records competing capacity models and future demand from Los Azules, El Pachón, Hualilán and other users.

What the public record does not provide is a single current multiuser operating picture that converts those legal rights into practical connection capacity under future project schedules. A commercial assessment requires updated project demand, technical scenarios, likely connection dates and the additional lines, transformation or compensation that later users may have to finance.

3. Which international suppliers are realistically positioned to compete for the transmission packages?

The regulatory record identifies a broad supplier market covering 500 kV and 220 kV GIS, large power transformers, reactors, protection and automation, communications, towers, conductors, OPGW, foundations, testing and specialist power-system studies. It does not identify the eventual winners.

Suppliers need to know the expected procurement route, incumbent relationships, qualification standards, local subcontracting requirements, import needs, high-altitude construction capabilities and which competitors are already positioned with Vicuña, Transener or likely contractors. That requires supplier and competitor mapping beyond the published regulatory file.

Where published information stops

Resolution 330 and the underlying regulatory record establish the approved access, principal transmission assets, priority framework and many technical requirements. They do not provide a complete current view of tender timing, package ownership, bidder lists, supplier qualification, incumbent vendors, EPC or EPCM structure, commercial terms, local subcontracting expectations or the practical capacity available for later mining projects.

Those gaps are where targeted market research becomes useful. Procurement monitoring, contractor and supplier mapping, primary interviews, local verification and project-specific infrastructure analysis can translate an approved corridor into a commercial view of who buys what, when and under which conditions.

Josemaría infrastructure and supplier research

Econosur can extend this public case analysis into targeted research for equipment manufacturers, engineering companies, contractors, investors and industrial suppliers evaluating the Josemaría corridor and the wider San Juan copper infrastructure market.

Procurement and tender trackingTrack announced and emerging packages, tender timing, prequalification signals, award status and changes in the execution schedule.
Buyer and contracting-route mappingIdentify which decisions sit with Vicuña, Transener, EPC or EPCM contractors and other project entities for selected equipment and service packages.
EPC, EPCM and contractor mappingMap engineering firms, construction contractors, transmission specialists and principal bidders positioned around the project.
Supplier qualification researchInvestigate registration, technical standards, safety requirements, documentation, local presence and other qualification conditions relevant to a defined supplier category.
Equipment demand mappingTranslate the approved infrastructure into demand categories for GIS, transformers, protection, automation, towers, conductors, OPGW, reactors and specialist services.
Local partner and subcontractor mappingIdentify Argentine engineering, construction, logistics and technical-service firms that may participate in local execution or subcontracting.
Competitor and incumbent supplier checksAssess which international and local suppliers are already visible around comparable Argentine transmission projects, contractors and mining clients.
Primary interviews and local verificationUse targeted conversations with suppliers, contractors, sector specialists and relevant market participants to test conditions not visible in public documents.
Grid-capacity and project-dependency researchCompare project demand, connection timing and infrastructure dependencies for Josemaría, Los Azules and other San Juan mining developments.
Commercial research synthesisCombine public documents, company information, interviews and local checks into a focused brief for a defined equipment, infrastructure or supplier question.
Sources and evidence limits

This case analysis relies primarily on official regulatory documents, the public-hearing transcript and Resolution 330/2026. Positions attributed to Vicuña, EPRE, Andes, Barrick, Gualcamayo, Casposo, Hualilán or La Rioja are presented as positions placed in the administrative record. Resolution 330 is used separately to identify the regulator’s final decision in this access and expansion proceeding.

Official sources

Corporate and Econosur context

Status note: Resolution 330/2026 is the federal regulatory decision for the access and expansion proceeding reviewed here. It should not be confused with construction completion, project sanction or procurement awards. The resolution itself requires additional technical compliance and easement steps, while future multiuser capacity and later mining connections remain dependent on project schedules and further system development. Sources were updated through 18 August 2026.

Infrastructure determines which copper project can move first

Resource size does not allocate electricity. Project readiness depends on nodes, lines, transformation, system strength, access rights and the commercial sequence of procurement.

Econosur researches procurement routes, contractor structures, supplier qualification, infrastructure dependencies and commercial conditions around mining projects in Argentina and South America.

Explore Custom Market Analysis

Frequently asked questions

What is the Josemaría power corridor?

It is a transmission package centered on the federal expansion authorized by Resolution 330/2026 to supply Josemaría Phase 1. The approved works include upgrades at Nueva San Juan, a new 500 kV yard and transformer at Rodeo, a new 167-kilometre 500 kV line to Chaparro and a new 500/220 kV GIS substation at Chaparro, with two 220 kV line exits toward Josemaría.

How much electricity does Josemaría initially require?

The access procedure concerns an initial demand of approximately 260 MW for Josemaría Phase 1. At the June 2026 hearing, Vicuña stated that project demand could later rise to around 400 MW and approximately 700 MW through successive stages.

What priority did Resolution 79/2026 grant to Vicuña?

Resolution 79 granted priority over 90 per cent of the capacity that CAMMESA classified as remaining on the Nueva San Juan–Rodeo corridor, plus up to 90 per cent of the new Rodeo–Chaparro line and the new Chaparro substation. The priorities were granted for 25 years from commercial operation of the relevant works.

Why is the 545.7 MVA figure disputed?

It is derived from 90 per cent of a modelled remaining capacity equal to 71 per cent of an assumed 854 MVA corridor capacity. Andes Corporación Minera argued that 854 MVA was not a measurement under current operating conditions and came from a model using an infinite-power-bus assumption that CAMMESA itself described as not matching the system’s current condition.

What did the Los Azules multiuser model claim?

A study commissioned by Andes Corporación Minera modelled simultaneous 2030 demand from Vicuña/Josemaría at 260 MW, Los Azules at 140 MW and El Pachón at 300 MW. Andes stated that the resulting corridor capacity was between 645 and 745 MVA. These are the objector’s study results, not a final regulatory finding.

Why do earlier mining investors object?

EPRE San Juan and earlier mining investors argued that the existing Nueva San Juan–Rodeo corridor was financed through public funds, electricity-user contributions and private mining contributions. They therefore seek recognition of historical financial rights, system mitigation and protection of capacity for existing and future users.

Who would operate the new 500 kV infrastructure?

The new federal-jurisdiction works would become part of the Argentine interconnected system and be operated and maintained by Transener under the regulatory framework. Vicuña would finance and promote the expansion but would not become the transmission-system operator.

Has the Josemaría grid dispute been resolved at federal regulatory level?

Yes for the access and expansion proceeding reviewed here. Resolution 330/2026 rejected the filed objections, authorized 260 MW of access for Josemaría Phase 1, issued the Certificate of Public Convenience and Necessity for the expansion and ratified Vicuña’s priority rights. Technical compliance, construction execution, project sanction and future capacity requirements for other users remain separate questions.

Which Josemaría power packages are closest to procurement, and who controls each buying decision?

Resolution 330 and the regulatory record define the main infrastructure and equipment layers, but they do not provide a complete current view of tender sequencing, package ownership, bidder lists, prequalification or award status. Those points require procurement monitoring, contractor mapping and direct market checks.

How much usable grid capacity will remain for Los Azules and other San Juan projects after Vicuña’s priority is applied?

Resolution 330 ratifies the priority structure and states that Vicuña’s priority applies to incremental capacity, but the public record does not provide a single final multiuser operating scenario for all future mining demand. Current capacity, future connections and additional expansion needs require technical and project-specific validation.

Which international suppliers are realistically positioned to compete for Josemaría’s transmission packages?

The public regulatory file identifies demand for 500 kV and 220 kV equipment, transformers, protection, automation, transmission structures and specialist engineering, but it does not establish the final supplier field, procurement route, local subcontracting requirements or incumbent positions. Supplier and contractor mapping is required for a commercial assessment.

Scroll to Top